UTICA BOILERS UBSSC-050 Installation, Operation & Maintanance Manual page 33

Wall mounted gas boiler
Table of Contents

Advertisement

9-6 Control Module J7 Connector
9 - START UP PROCEDURE
9.7 Complete Start Up Procedure
1.
2.
3.
4.
33
Reset control parameters to operating settings if
adjusted to allow startup and operation test.
Follow instructions TO TURN OFF GAS TO APPLIANCE
if boiler is not being placed into immediate
operation.
Enter installer information on Warranty Registration
Card.
Gather all instructions, manuals, wiring diagrams,
warranty registration card and other supporting
information. Review with user and/or affi x in
conspicuous location adjacent to boiler.

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ubssc-075Ubssc-100Ubssc-150Ubssc-200

Table of Contents