4.1 PLANNING
The layout for installing the 1200 Radar should be planned to give the best opera-
tion and 'service aboard your particular ship. In general, the Scanner Unit should be
mounted atop the wheelhouse or bridge as high as possible. The Display Unit should be
installed in the wheelhouse at a convenient viewing position.
A 10 meter length of Vinyl-covered, shielded, 11 conductor cable is furnished for
interconnecting the two main units (Scanner and Display).
This length of cable should be sufficient to fabricate the cable runs required on most
small ships: additional cable may be ordered from RAYTHEON. The maximum length
cable from the Scanner Unit to the Display Unit should not exceed 20 meters.
Figure 101 shows the General System drawing for the 1200 Radar.