Lopi Yankee Bay Instruction Manual page 9

Pellet insert
Hide thumbs Also See for Yankee Bay:
Table of Contents

Advertisement

Remove the correct knock-outs in the hopper walls following the directions below.
If you are using hopper extension position F, remove
the top knock-out. If using position E, remove the
second knock-out, (etc...). The second-to-bottom
knock-out is position B.
Position F Knock-Out
Position E Knock-Out
Position D Knock-Out
Position C Knock-Out
Position B Knock-Out
Position A Knock-Out
Re-install the hopper walls following the directions below.
Attach the hopper top following the directions below.
Before installing the
hopper top, use a center-
punch (or other suitable
tool) to remove the
appropriate knock-outs
on the hopper top.
Re-attach the hopper top to the
hopper walls using the screws
included with the insert.
© Travis Industries
Installation
NOTE: This hopper extension is in position D.
4 0 8 0 7 2 3
Use a center-punch (or other suitable
tool) to remove the appropriate knock-
outs in the hopper walls (punch the
holes out from the inside). Make sure
to support the hopper walls while
removing the knock-outs. There are 11
knock-outs for each position.
HINT:
Attach one screw to each
side to align the hopper walls. Then
install the remaining screws.
1 0 0 - 0 1 1 4 5
9

Advertisement

Table of Contents
loading