1.5"
3" Offset
1"
Offset
1.5" Clearance
Figure 27 - OSR58-30 Offset and Return
for (V)CD36T Series Units
Flat Ceiling Installation
1. Cut a 11
/
" square hole in ceiling using
1

locating hole as a center point. The open-
ing should be framed to 11
(292 mm x 292 mm) inside dimensions,
as shown in Figure 12 on page 11 using
framing lumber the same size as ceiling
joists. If area above ceiling is an insulated
ceiling or an attic, nail firestop from top
side. This prevents loose insulation from
falling into required clearance space. If
area above ceiling is a living space, in-
stall firestop below framed hole. Firestop
should be installed with no less than three
nails per side (see Figure 28).
2. Assemble desired lengths of pipe and
elbows necessary to reach from fireplace
flue up through firestop. Be sure all pipe
and elbow connections are fully twist-
locked (see Figure 11, page 12).
3. Cut a hole in the roof using locating hole as
a center point. (Cover any exposed open
vent pipes before cutting hole in roof.) The
11
/
" x 11
/
" hole must be measured on
1
1


the horizontal; actual length may be larger
depending on pitch of roof. There must
be a 1" clearance from the vent pipe to
combustible materials. Frame opening as
shown in Figure 12, page 12.
4. Connect a section of pipe and extend up
through hole.
18
VENTING INSTALLATION
1"
1" Clearance
20°
C L
/
" x 11
1


www.desatech.com

Continued
Note: If an offset is needed to avoid obstruc-
tions, you must support vent pipe every 3
feet. Use wall straps for this purpose (see
Figure 26, page 17). Whenever possible,
use 45° elbows instead of 90° elbows. The
45° elbow offers less restriction to the flow
of flue gases and intake air.
5. Place flashing over pipe section(s) ex-
tending through roof. Secure base of
flashing to roof and framing with roofing
nails. Be sure roofing material overlaps
top edge of flashing as shown in Figure
26, page 17. There must be a 1" clearance
from vent pipe to combustible materials.
3.5"
6. Continue to add pipe sections until height
of vent cap meets the minimum building
code requirements described in Figure 10
on page 9.
Note: You must increase vent height for
steep roof pitches. Nearby trees, adjoining
rooflines, steep pitched roofs and other
similar factors may cause poor draft or
down-drafting in high winds. Increasing
vent height may solve this problem.
/
"
1

7. Twist-lock vent cap onto last section of
vent pipe.
Note: If vent pipe passes through any oc-
cupied areas abovethe first floor, including
storage spaces and closets, you must enclose
pipe. You may frame and sheetrock enclosure
with standard construction material. Make
sure and meet minimum allowable clearances
to combustibles. Do not fill any required air
spaces with insulation.
If area above is an attic or insulated area,
install firestop above framed hole.
If area above is a living space, install
firestop below framed hole.
Figure 28 - Installing Firestop
116035-01J