Built-in clock adjustment
NOTE

PV calibration

Input CH No. select
Gain No. select
A: 2 digits of calendar year
B: Month
C: Day
D: Hour (24 hour system)
E: Minute
F: Second
1. ↑, ↓, ←, →, keys are used to change the values, and ENTER key is used to store
the values.
2. Clock is still progressing the operation even after the calibration step is moved to this
built-in clock adjustment item. After entering the changing mode by ENTER key,
the clock stops.
3. After pressing ENTER key, the clock starts from 0 second.
4. Writing to EEPROM is not necessary.
Scroll ↑, ↓, ←, →, keys to show (1011) on upper display, then press ENTER key.
Press SETUP key until the PROG/SEG display shows (01-01).
Input the channel No. by ↑, ↓, ←, →, keys ( ENTER key not required).
Press SETUP key until the PROG/SEG display shows (01-02). Connect calibration
device (See Section "12-3 Set Up").
Input the gain number (See Table 12-9 and Table 12-10) by scrolling ↑, ↓, ←, →, keys
the upper display ( ENTER key not required).
)
*
PROG
PV
DEV
OUT
CYC
SP
TM
SYN
+
,
Figure 12-4.
Example:
1993 ........................93
April ........................04
5th day .....................05
3PM ........................15
6 minutes ..................06
Not changeable
Table 12-8.