Single Module and 1+1 Parallel System
3.

Chapter 3 - Installation Procedure

3.1

Introduction

Do not apply electrical power to the UPS equipment before the arrival of the commissioning engineer.
The UPS equipment should be installed by a qualified engineer in accordance with the information contained in
this chapter and the drawing package shipped inside the UPS cabinet
Special care should be taken when working with the batteries associated with this equipment. When connected
together, the battery terminal voltage will exceed 400 Vdc and is potentially lethal.
Eye protection should be worn to prevent injury from accidental electrical arcs.
Remove rings , watches and all metal objects.
Only use tools with insulated handles.
Wear rubber gloves.
If a battery leaks electrolyte, or is otherwise physically damaged, it must be replaced, stored in a container
resistant to sulfuric acid and disposed of in accordance with local regulations.
If electrolyte comes into contact with the skin the affected area should be washed immediately
This chapter contains information regarding the positioning and cabling of the UPS equipment and
batteries.
Because every site has its peculiarities, it is not the aim of this chapter to provide
step-by-step installation instructions, but to act as a guide as to the general
procedures and practices that should be observed by the installing engineer.
document in response to "powersure ups"
WARNING
WARNING
WARNING
Battery hazards
Chapter 3 - Installation Procedure
Introduction
Page 3-1
Issue 6
(03/98)