Installing the hardware
C
Clearance for 19" installation plane
C1
Front 19-inch installation plane
C2
Rear 19-inch installation plane
D
Space for cabling (cable space depth) and ventilation
E
Space for control panel and ventilation
F
Space for right and left support systems
P
PRIMERGY installation depth
a1
Front left support upright
a2
Front right support upright
b1
Rear left support upright
b2
Rear right support upright
4.3.1

Installation in PRIMECENTER/DataCenter rack

For installation in a PRIMECENTER/DataCenter rack, the following parts are
required:
– Two 3-HU Support brackets (for the EMEA market)
– Two carrier rails (mounted)
– Two holding-down clamps
I
– The descriptions and figures in this section refer to the current
support system. For other support systems you will find the
appropriate description in the packaging of the rack mounting kit.
For information on mounting of the rails in the 19-inch standard rack
(for the Japanese market) please refer to the "Rack mount guide".
– General information regarding server installation in the rack is
included in the technical manual for the appropriate rack.
– For information on mounting of the server in the 19-inch standard rack
(for the Japanese market) please refer to the "Rack mount guide".
When mounting the left carrier rail in the PRIMECENTER/DataCenter rack, the
supplied support brackets must first be mounted on the rear left support upright
flush with the bottom edge of the device.
Ê Read the installation guide in the technical manual for the corresponding
rack.
44