Air purging with vacuum pump
1. Check that each tube(both liquid and gas side tubes) between the indoor and
outdoor units have been properly connected and all wiring for the test run has
been completed. Remove the service valve caps from both the gas and the
liquid side on the outdoor unit. Note that both the liquid and the gas side
service valves on the outdoor unit are kept closed at this stage.
2. When relocating the unit to another place, perform evacuation using vacuum
pump.
3. Pipe length and refrigerant amount:
Connective
pipe length
Less than 25'
Use vacuum pump.
25'~65.6
'
Use vacuum pump.
25'~98.4'
Use vacuum pump.
Caution in handling the packed valve integrated in the outlets of
outdoor unit.
1. Operation of opening packed valve: Open the valve stem until it hits against
the stopper. Do not try to open it further.
2. Operation of closing packed valve: Securely tighten the valve stem with a special
tool. Then securely tighten the valve stem cap with a spanner or the like. Refer to
tightening torque table in page 17
Note: There is a charging port integrated in the low side outlet, but not in the
high side outlet. The low side outlet is shown in the sketch map below.
Refrigerant
Outdoor unit
A
B
Packed valve
Air
purging
for valve stem cap tightening torque
Indoor unit
Gas
C
D
Half union
Additional amount of
refrigerant to be charged
R410a: 1.058ozs (Pipe length-25')
( 12000 Btu's)
<
R410a: 0.705ozs (Pipe length-25')
(=18000 Btu's)
R410a: 1.058ozs (Pipe length-25')
(=21500 Btu's)
Valve body
Charge port
Valve stem
Stopper
Flare nut
Cap
Air purging
22

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Frs12pys1Frs184ys2Frs18pys2Frs224ys2Frs22pys2

Table of Contents