Step 6: Install end panel (E) to the left side of the array.
a. Set into the horizontal panel mount angle (K) and tight to the vertical panel mount channel (I) and make
plumb/level along the array plane.
E
I
b. Insert (2) PN 416081 screws through the bottom holes of end panel (E) and
horizontal panel mount angle (K).
c. Insert PN 416081 screws through the side, end panel (E) and vertical panel
mount channel (I), as shown in the image above.
Do not fully tighten the screws. When all panels are installed, go back through all
the seams to tighten screws (Step 13).
®
A
416081 - 1/4 x 1/2 in. long screws
NOTE
K
I
K
Modular Open Array