Commissioning - Siemens 6AV3991-1AJ02-0AB0 Equipment Manual

Table of Contents

Advertisement

Commissioning

Flowchart
The guide to commissioning, depicted below, describes the individual steps
required for commissioning Touch Panels TP27 and TP37. Figure 13-1 illus-
trates the most important steps for the initial startup, recommissioning and nor-
mal operation of the Touch Panels.
Initial startup
Neither a configuration nor
firmware is available on the
Touch Panel.
Download configuration data to the Touch Panel
ProTool
COM1/2
Figure 13-1 Commissioning flowchart
TP27, TP37 Equipment Manual
Release 01/00
Recommissioning
The Touch Panel already has
a configuration but must now
use a new configuration or
firmware.
Switch on the Touch Panel's power supply
Set the Touch Panel to Download
mode in the startup phase (refer to
Section 13.2)
Start screen
Normal operation
The Touch Panel is oper-
ated with the loaded config-
uration.
Touch Panel
SIMATIC
13
13-1

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simatic hmi tp37Simatic hmi tp27

Table of Contents