For feed system (manual) (continued)
Workflow
Sieve-load material
feeding from manual
aspiration hose
Build-unit load
Build-unit load
Workflow
Build-unit load
Build-unit load
Build-unit load
Build-unit load
Ordering information
Contact the 3D Metal Expertise Center of your region for HP Proto supplies. Details are included in the
HP Metal Jet Printing Solution Support document.
Step
User vacuums powder
using manual aspiration
hose
Step
User requests load:
User introduces quantity to
load and recipe. Selects
Start
User requests load:
User introduces quantity to
load and recipe. Selects
Start
User requests load:
User introduces quantity to
load and recipe. Selects
Start
Unit fails to dispense
Failure
Aspiration stopped. Target
mass not delivered
Failure
Door is not locked
Selected quantity to load is
not possible (greater than
capacity)
Build Unit first position not
detected
Unit fails to dispense:
●
Interrupted by user
Out of material
●
●
Power cut
●
Failure of an element
or a sensor
●
Not properly levelling.
0033-0001-0005
Refiller – Levelling
time out
Manual recovery
If the error appears after
not having transported any
material for a long time,
the machine detects it and
stops transportation.
If the error appears during
powder transportation,
see the Continuous slow
aspiration failure.
Manual recovery
Check if the door is closed.
Introduce a value within
machine limit.
Check if the Build Unit is
inserted and in contact
with first position datum.
Rearm.
Workflow for Build Unit
recovery will be executed.
Then, extract the Build Unit.
Build-unit load
105