5. Tighten cable glands well to obtain optimum sealing.
5.3
Installation check
The meter is now ready to go into normal operation - for commissioning and setting of
parameters refer to the relevant transmitter manual.
Before commissioning it must be checked that:
● The device has been installed and connected in accordance with the guidelines provided
See also
Connecting (Page 33)
SITRANS F M MAG 3100 sensor
Operating Instructions, 09/2012, A5E03005599-02
CAUTION
Unscreened cable ends
Keep unscreened cable ends as short as possible.
CAUTION
Prevent interference
Separate electrode and coil cables to prevent interference.
WARNING
Use in hazardous area
Connect mains protective earth to the PE terminal in accordance with the above
diagram in order to obtain potential equalization.
WARNING
Mount terminal box lid before power up.
previous in this chapter and in chapter 4 Installing/mounting .
Connecting
5.3 Installation check
37