To Perform A Gas Pressure Test; To Perform A Test Run On The Gas Boiler - Daikin Altherma EHYHBH05A Series Installer's Reference Manual

Hybrid heat pump
Table of Contents

Advertisement

12
|
Commissioning

12.4.6 To perform a gas pressure test

12.4.7 To perform a test run on the gas boiler

Installer reference guide
204
1 Go to the underfloor heating screed dryout screen.
2 Press
.
3 Press
to interrupt the program.
4 Select OK and press
Result: The underfloor heating screed dryout program is stopped.
When the program is stopped due to an error, an operation switch-off, or a power
failure, you can read out the underfloor heating screed dryout status.
5 Go to [A.7.2]:
screed dryout > Dryout status > Stopped at and followed by the
last executed step.
6 Modify and restart the execution of the program.
1 Connect a suitable gauge on the gas valve. Static pressure MUST be 20 mbar.
2 Select test program " ". See
4
boiler"  [
  204]. Static pressure MUST be 20  mbar (+ or – 1  mbar). If the
working pressure is <19 mbar, the gas boiler output will be reduced and the
correct combustion reading may NOT be obtained. Do NOT adjust the air and/
or gas ratio. To obtain sufficient working pressure, gas supply MUST be
correct.
INFORMATION
Make sure the working inlet pressure does NOT interfere with other gas appliances
installed.
The gas boiler has a test run function. Activating this function results in the
activation of the indoor unit pump, as well as the gas boiler (with a fixed fan
speed), without the control functions being actuated. The safety functions remain
active. The test run can be stopped by pressing
automatically after 10 minutes. To perform a test run, switch off the system with
the user interface.
.
> Installer
settings > Commissioning > UFH
"12.4.7  To perform a test run on the gas
EVLQ05+08CA + EHYHBH05A + EHYHBH/X08A + EHYKOMB33AA
and
simultaneously or will end
Daikin Altherma hybrid heat pump
4P355634-1G – 2022.09