Setting up an IRF fabric

You can use H3C IRF technology to connect and virtualize S6520X-EI or S6520X-HI switches into a
large virtual switch called an "IRF fabric" for flattened network topology, and high availability,
scalability, and manageability.
An S6520X-EI or S6520X-HI switch can set up an IRF fabric only with switches from the same switch
series.

IRF fabric setup flowchart

Figure4-1 IRF fabric setup flowchart
Plan IRF fabric setup
Install IRF member switches
Connect the grounding cable
and power cords
Power on the switches
Configure basic IRF settings
Connect the physical IRF ports
Standby switches reboot and
the IRF fabric is automatically
established
To set up an IRF fabric:
Step
1.
Plan IRF fabric setup
Start
End
Description
Plan the installation site and IRF fabric setup parameters:
Planning IRF fabric size and the installation site
Identifying the master switch and planning IRF member IDs
Planning IRF topology and connections
4-1