Checklist Before Commissioning; Checklist During Commissioning; To Perform A Test Run - Daikin RXTM30R2V1B Installer's Reference Manual

Hide thumbs Also See for RXTM30R2V1B:
Table of Contents

Advertisement

12
|
Commissioning

12.3 Checklist before commissioning

12.4 Checklist during commissioning

12.5 To perform a test run

Installer reference guide
54
During test operation, the outdoor unit and the indoor units will start up. Make
sure that the preparations of all indoor units are finished (field piping, electrical
wiring, air purge, ...). See installation manual of the indoor units for details.
After the installation of the unit, first check the items listed below. Once all checks
are fulfilled, the unit must be closed. Power-up the unit after it is closed.
The indoor unit is properly mounted.
The outdoor unit is properly mounted.
The system is properly earthed and the earth terminals are tightened.
The power supply voltage matches the voltage on the identification label of the unit.
There are NO loose connections or damaged electrical components in the switch box.
There are NO damaged components or squeezed pipes on the inside of the indoor and
outdoor units.
There are NO refrigerant leaks.
The refrigerant pipes (gas and liquid) are thermally insulated.
The correct pipe size is installed and the pipes are properly insulated.
The stop valves (gas and liquid) on the outdoor unit are fully open.
Drainage
Make sure drainage flows smoothly.
Possible consequence: Condensate water might drip.
The indoor unit receives the signals of the user interface.
The specified wires are used for the interconnection cable.
The fuses, circuit breakers, or locally installed protection devices are installed according to
this document, and have NOT been bypassed.
To perform an air purge.
To perform a test run.
INFORMATION
If the unit runs into an error during commissioning, see the service manual for the
detailed troubleshooting guidelines.
Prerequisite: Power supply MUST be in the specified range.
Prerequisite: Test run may be performed in cooling or heating mode.
RXTM-R_RXTP-R_ARXTP-R_RXTA-B
R32 split series
4P518023-11H – 2021.03