6.9
Bearing­monitoring system
The bearing­monitoring device must be fitted by the customer.
6.10
Gear unit with oil­temperature monitoring system
Wire the temperature monitor electrically.
6.11

Final work

After installation of the gear unit check all screw connections for tight fit.
Check the alignment after tightening the fastening elements (the alignment must not have been
changed).
Any oil­drain cocks must be secured against accidental opening.
The gear unit must be protected against falling objects.
Protective devices for rotating parts must be checked for correct seating. Contact with rotating parts
is not permitted.
A potential equalisation in accordance with the applying regulations and directives must be carried out!
If no threaded holes for earth connection are available on the gear unit, other appropriate measures
must be taken. This work must always be done by specialist electricians.
Cable entries must be protected against moisture.
Check that protective measures have been taken!
Observe the operating instructions to the add­on parts.
BA 5814 en 09/2014
40 / 61