After installation has been completed, it is recommended that the Air Handler be checked against the following
checklist.
1. Make sure power is "OFF" at power disconnect
switch ........................................................................... [ ]
2. Check all field wiring for tight connections.
See that grounding of unit is in accord with code ..... [ ]
3. Make sure unit suspension (if used) is secure
and that there are no tools or loose debris in,
around or on top of the unit ....................................... [ ]
4. Check all duct outlets; they must be open
and unrestricted .......................................................... [ ]
5. Check drain lines and be sure all joints are tight [ ]
SUPPLEMENTARY HEATERS CHECKOUT PROCEDURES,
1. Be sure the disconnect switch is "OFF", and safety label (if any) is attached ............................... [ ]
2. Check on field wiring for tight connections and grounding according to codes ............................ [ ]
3. Check circuit protection for proper size per nameplate specifications .......................................... [ ]
4. Check control box panel — in place and secured ........................................................................... [ ]
NOTE: OPERATION OF HEATERS MUST BE CHECKED DURING THE OPERATION CHECK OF THE
TOTAL SYSTEM.
!
ELECTRICAL SHOCK HAZARD
LOCK UNIT DISCONNECT SWITCH IN OPEN POSITION
BEFORE SERVICING UNIT. FAILURE TO FOLLOW THIS
WARNING COULD RESULT IN PROPERTY DAMAGE,
PERSONAL INJURY, OR DEATH.
Trane
6200 Troup Highway
Tyler, TX 75707
www.trane.com
J. CHECKOUT PROCEDURES
IF USED DOES HEATER REQUIRE A SPECIAL CIRCUIT?
SEE "LIMITATIONS AND RECOMMENDATIONS"
WARNING
6. Make sure secondary drain pan is installed ....... [ ]
7. Check power supply for correct requirements
per unit nameplate .................................................... [ ]
8. Check filters for proper size. Inform owner of
proper procedure for removal and reinstallation ...... [ ]
9. Energize
the
system
its operation; make any necessary adjustment ........ [ ]
10. Instruct owner, engineer (if possible) on proper
operating
procedure
Manual with owner .................................................... [ ]
The following warning complies with State of California law, Proposition 65.
WARNING:
fiberglass wool insulation! Fiberglass dust and ceramic
fibers are believed by the State of California to cause
cancer through inhalation. Glasswool fibers may also
cause respiratory, skin, or eye irritation.
PRECAUTIONARY MEASURES
Avoid breathing fiberglass dust.
Use a NIOSH approved dust/mist respirator.
Avoid contact with the skin or eyes. Wear long-
sleeved, loose-fitting clothing, gloves, and eye
protection.
Wash clothes separately from other clothing: rinse
washer thoroughly.
Operations such as sawing, blowing, tear-out, and
spraying may generate fiber concentrations requiring
additional respiratory protection. Use the appropriate
NIOSH approved respirator in these situations.
FIRST AID MEASURES
Eye Contact
-
Flush eyes with water to remove dust.
If symptoms persist, seek medical
attention.
Skin Contact -
Wash affected areas gently with soap
and warm water after handling.
The manufacturer has a policy of continuous product and product data
improvement, and it reserves the right to change design and specifications
without notice.
and
carefully
and
leave
Use
and
This product contains
observe
Care
05/10

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents