1
Initial situation
3
Push the left-hand control gate to the right.
184/214
Feeder earthing
Revision 06 • INSTALLATION AND OPERATING INSTRUCTIONS • 8DB10 • 864-5091.9
2
Push the selector gate to the left.
4
Switch the three-position disconnector to READY-TO-EARTH position
(insert the operating lever for the READY-TO-EARTH function and turn
180° clockwise).