Safety Relief Valve And Air Vent; Low Water Cutoff - UTICA BOILERS UCS-380 Installation, Operation & Maintenance Manual

Condensing gas fired floor or wall mounted boiler
Table of Contents

Advertisement

FIGURE 5-1 Safety Relief Valve Discharge Piping
Safety Relief Valve
Check Local Codes For
Maximum Distance To
Floor
FIGURE 5-2 System Piping - LWCO Probe Location
Viewed from Back of Boiler
MINIMUM
ACCEPTABLE
HEIGHT FOR
LWCO PROBE
System
Return
12" (305mm)
Maximum
Separation
5 - HYDRONIC PIPING
Burn and scald hazard. Safety relief valve could
discharge steam or hot water during operation.
Install discharge piping per these instructions.

5.3 Safety Relief Valve and Air Vent

System
Supply
Fire, explosion hazard. Mount boiler vertically or
slightly tilted backward to insure proper function of
low water cutoff. Failure to follow these instructions
could result in death or serious injury.
System

5.4 Low Water Cutoff

Supply
• Boiler is equipped with Low Water Pressure Switch.
• Low Water Cutoff (LWCO) probe location. See figure 5-2
• If using separate stand pipe, install air vent using tee to
• Arrange piping to prevent water dripping onto boiler.
• Connect probe signal wires to shutdown terminal (BL) on
Check Local Codes
For Maximum
Distance To Floor
11
!
WARNING
• Install safety relief valve using field supplied pipe
fittings. See figure 5-1
• Install safety relief valve with spindle in vertical position.
• Do not install shutoff valve between boiler and safety
relief valve.
• Install discharge piping from safety relief valve.
• Use ¾" or larger pipe.
• Use pipe suitable for temperatures of 375°F (191°C) or
greater.
• Individual boiler discharge piping shall be independent
of other discharge piping.
• Size and arrange discharge piping to avoid reducing
safety relief valve relieving capacity below minimum
relief valve capacity stated on rating plate.
• Run pipe as short and straight as possible to location
protecting user from scalding and properly drain piping.
• Install union, if used, close to safety relief valve outlet.
• Install elbow(s), if used, close to safety relief valve
outlet and downstream of union (if used).
• Terminate pipe with plain end (not threaded).
!
WARNING
for minimum probe height. Do not install shutoff valve
between boiler and LWCO probe..
avoid nuisance shutdowns.
control board.