Correcting The Mower Quality Of Cut; Frame Set Up - Toro 30326 Operator's Manual

Mid-size mower proline t-bar gear 15hp or 17hp with 44 in side discharge
Hide thumbs Also See for 30326:
Table of Contents

Advertisement

1
Figure 48
1. Sharpen at original
angle
2. Check the balance of the blade by putting it on a blade
balancer (Fig. 49). If the blade stays in a horizontal
position, the blade is balanced and can be used. If the
blade is not balanced, file some metal off the end of the
(Fig. 47).
sail area only
Repeat this procedure until the
blade is balanced.
1
Figure 49
1. Blade
Installing the Blades
1. Install the blade onto the spindle shaft
Important
The sail part of the blade must be pointing
upward, toward the inside of the mower to ensure proper
(Fig. 47).
cutting
2. Install the flat washer, lock washer and blade bolt
(Fig. 47).
Torque the blade bolt to 85–110 ft-lb
(115–140 NS m).
Correcting the Mower Quality
of Cut
If one deck blade cuts lower than the other, correct as
follows.
Tire air pressure is critical in these procedures.
Note:
Make sure all tires have correct pressure.
1. Disengage the PTO and set the parking brake.
2. Stop the engine, remove the key, and wait for all
moving parts to stop before leaving the operating
position. Disconnect the spark plug wire(s) from the
spark plug(s).
3. Adjust the tire pressure in all tires to specifications on
page 32.
m–1854
2
m–1855
2. Balancer
(Fig. 47).
36
4. Check that the blades and spindle shafts are not bent.
Refer to Checking for Bent Blades on page 35.
5. Set the height-of-cut to the 4 inch (101.6 mm) position.
Refer to Adjusting the Height-Of-Cut in the Operation
section.
6. Perform steps in the following sections Frame Set Up,
Checking Front–to–Rear Pitch and Checking
Side–to–Side Leveling.

Frame Set Up

Checking Carrier Frame and Deck
Alignment
1. Disengage the PTO and set the parking brake.
2. Stop the engine, remove the key, and wait for all
moving parts to stop before leaving the operating
position.
3. Place a long straight edge on top of the engine deck as
shown in figure 50.
4. At the carrier frame cross tube, measure location A
height (Fig. 50). This measurement must be 1–5/16 inch
(33 mm), plus or minus a 1/4 inch (6 mm).
5. If the height at location A is not correct, adjustment is
needed.
6. Loosen the carrier frame mounting bolts on both sides
of the machine (Fig. 50).
7. Align the carrier frame and engine deck to match
1–5/16 inch (33 mm), plus or minus a 1/4 inch (6 mm)
at location A (Fig. 50).
8. Tighten the carrier frame mounting bolts on both sides
of the machine.

Advertisement

Table of Contents
loading

This manual is also suitable for:

30327

Table of Contents