Connection diagram of „Stropuva" boiler to another boiler, water
6.2
1. Triple D25
2. Triple D25 x D15
4. Elbow D25 V/i
5. Nipple D25
6. Adapter D25 x D15
7. Circulation pump installation
kit
D25
8. Separable connection D25 V/i
9. Automatic bleeding device
10. Balance valve D25 V/i
11. Horizontal monometer 1/4"
12. Adapter D15 x 1/4"
13. Ball valve V/i 1"
14. Circulation pump
15. Thermostatic head 20 - 50 °C
For boilers S7, S10, S12, S20, S7 BIO, S10 BIO, S20 BIO and S10U, S12U, S20U, nodes are
assembled from parts D20. For boilers S30, S30 BIO and S30U, S40, S40 BIO and S40U nodes
are assembled from parts D25.
TECHNICAL PASSPORT, INSTALLATION AND MAINTENANCE INSTRUCTION
heater and floor heating
- 10 pcs.
- 3 pcs.
- 2 pcs.
- 15 pcs.
- 3 pcs.
- 1 pcs.
- 2 pcs.
- 1 pcs.
- 1 pcs.
- 1 pcs.
- 1 pcs.
- 3 pcs.
- 1 pcs.
- 1 pcs.
18. Filling valve i/i 1/2"
19. Release valve 1/2
20. Brass disc valve V/V 1"
21. Adapter D32 x D25
22. Thermostatic valve
23. Valve 1,5 bar
F - to/out of floor heating
B - to/out of water tank
K2 - to/out of other boilers
Figure 11
- 1 pcs.
- 1 pcs.
- 2 pcs.
- 2 pcs.
- 1 pcs.
- 1 pcs.
.
.
.
13