7 Piping installation
In this chapter
7.1 Preparing refrigerant piping
7.1.1 Refrigerant piping requirements
ARXM50-71+RXM42~71R2V1B + RXP50~71M2V1B + RXA42+50B2V1B +
RXF50+60B2V1B + RXF71A2V1B + RXJ50N2V1B + ARXF50~71A2V1B
R32 split series
4P513661-9J - 2020.05
7.1
Preparing refrigerant piping ...................................................................................................................................................
7.1.1
Refrigerant piping requirements ...........................................................................................................................
7.1.2
Refrigerant piping insulation..................................................................................................................................
7.1.3
7.2
Connecting the refrigerant piping..........................................................................................................................................
7.2.1
7.2.2
7.2.3
7.2.4
Pipe bending guidelines .........................................................................................................................................
7.2.5
To flare the pipe end..............................................................................................................................................
7.2.6
7.2.7
7.3
Checking the refrigerant piping..............................................................................................................................................
7.3.1
7.3.2
7.3.3
To check for leaks...................................................................................................................................................
7.3.4
To perform vacuum drying ....................................................................................................................................
INFORMATION
Also read the precautions and requirements in the
4
precautions" [
NOTICE
The piping and other pressure-containing parts shall be suitable for refrigerant. Use
phosphoric acid deoxidised seamless copper for refrigerant.
▪
Piping material: Phosphoric acid deoxidised seamless copper.
▪
Flare connections: Only use annealed material.
▪
Piping diameter:
Models
Liquid piping
RXM71R
Ø6.4 mm (1/4")
ARXM71R
Ø9.5 mm (3/8")
RXM42R
Ø6.4 mm (1/4")
Other
Ø6.4 mm (1/4")
▪
Piping temper grade and thickness:
Outer diameter (Ø)
6.4 mm (1/4")
Annealed (O)
9.5 mm (3/8")
12.7 mm (1/2")
15.9 mm (5/8")
(a)
Depending on the applicable legislation and the maximum working pressure of the unit
(see "PS High" on the unit name plate), larger piping thickness might be required.
5].
Temper grade
≥0.8 mm
≥1 mm
7
Piping installation
|
"2 General safety
Gas piping
Ø15.9 mm (5/8")
Ø15.9 mm (5/8")
Ø9.5 mm (3/8")
Ø12.7 mm (1/2")
(a)
Thickness (t)
Installer reference guide
35
35
36
36
36
37
37
38
39
39
40
41
42
42
42
43
43
Ø
t
35