REINSTALLATION
1. Install the side/top support bracket, 1, with the
capscrews, 2, and washers removed during
disassembly.
2. Install the dust shields, 1, and new O rings, 2,
around each hydrostatic pump control arm.
3. Install the neutralizer cam arms, 1, over the
trunnion shafts, with the bearings facing the rear
of the unit. Secure the arms with the 3/8" Grade
8 bolts, 3, lockwashers and nuts removed during
disassembly. Tighten to 65 N⋅m (48 ft. lbs.).
4. Fill the pump assembly with oil through the case
drain port. Install all the port fittings, but do not
tighten the fitting nuts at this time as aligning
hoses and fittings will be required.
Refer to the "Hydraulic System Cleaning After a
Rebuild" section of this manual before installing
the pump assembly in the loader.
SECTION 29 - HYDROSTATIC TRANSMISSION
29-54
1
19998046
19998073
2
1
3
2
19998075
1
103
2
1
104
2
3
1
2
105