5. See
Figure
6-8. Arrow right and press center
button to Confirm.
Figure 6-8. Enabling Inverter (3 of 4)
6. See
Figure
6-9.
The inverter is enabled. It will cre-
ate voltage at the DC terminals and begin commu-
nicating over REbus.
NOTE: Per UL1741, the Generac PWRcell Inverter may
wait five minutes or longer before beginning to export
power after the inverter has been enabled.
Figure 6-9. Inverter Enabled (4 of 4)
7. Enable all other Rebus devices connected to the
system by repeating steps 1-5 for each device.
NOTE: If the system includes battery storage, islanding
must be enabled to allow the inverter to provide power
during grid outages. See
information.
Generac REbus Beacon Setup
Generac REbus Beacon allows the Generac PWRcell
system to manage energy production and storage over
the course of the day. This is called Time of Use (TOU)
energy management. To take advantage of this function-
ality, Generac PWRcell must include a Generac PWRcell
battery and a reliable connection to the Internet via an
Ethernet connection to a router. See
more information.
Installation Manual for Generac PWRCell Inverter
010017
010013
Enabling Islanding
for more
Ethernet Setup
Configuring and Running a TOU Schedule
1. See
Figure
device page and press the center button to enter
the device menu.
Figure 6-10. Configuring TOU Schedule (1 of 4)
2. See
Figure
highlight Mod. Settings and press the center button
to enter the settings menu.
Figure 6-11. Configuring TOU Schedule (2 of 4)
3. See
Figure
highlight Access Code and press the center button
to select.
4. Use the up and down arrows to set the Access
Code to 57, and press the center button.
NOTE: The access code is valid for five minutes. After
five minutes, the access code must be entered again to
enable changes.
for
Figure 6-12. Configuring TOU Schedule (3 of 4)
Commissioning and Setup
6-10. Navigate to the Generac Beacon
6-11. Use the up and down arrows to
6-12. Use the up and down arrows to
010109
01010
010111
23