Steps - commissioning, inspection and maintenance

Commissioning steps
Inspection steps
Maintenance steps
2. Filling the trap with water..................................................................................................
tightness............................................................................................................................. 10
4. Checking the electrical connections................................................................................ 11
5. Checking the gas type....................................................................................................... 11
6. Setting the gas type........................................................................................................... 12
7. Commissioning the system............................................................................................... 12
8. Checking the flue gas damper.......................................................................................... 13
9. Reducing the maximum heating output (if required)...................................................... 14
10. Checking the static pressure and supply pressure........................................................ 14
12. Measuring the CO content................................................................................................. 17
13. Measuring the flue gas temperature................................................................................. 17
14. Checking the ionisation current....................................................................................... 17
15. Shutting down the system................................................................................................. 18
16. Opening the boiler.............................................................................................................. 19
17. Opening the combustion chamber................................................................................... 20
18. Cleaning the combustion chamber and heating surfaces............................................. 20
19. Cleaning the burner........................................................................................................... 22
20. Checking the burner door................................................................................................. 22
21. Checking the burner gauze assembly.............................................................................. 23
22. Checking the ignition electrodes and ionisation electrode........................................... 24
23. Fitting the burner................................................................................................................ 24
24. Closing the combustion chamber.................................................................................... 24
25. Checking the gas train valves for tightness.................................................................... 25
26. Checking the gas train filter element............................................................................... 26
27. Checking the filter element in the gas line...................................................................... 26
28. Checking the gas connections for tightness................................................................... 26
29. Cleaning the condensate drain pipe and trap................................................................. 27
31. Closing the boiler casing................................................................................................... 28
32. Checking the expansion vessel........................................................................................ 28
33. Checking the water quality................................................................................................ 28
34. Checking the gaskets on the flue gas side...................................................................... 28
35. Performing final checks..................................................................................................... 29
37. Checking the mixer for ease of operation and leaks...................................................... 29
Commissioning, inspection, maintenance
content............................................................................................... 16
2
Page
9
9
7

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vitocrossal cru seriesVitocrossal cru 1000

Table of Contents