Piping Installation Point - Daikin VRV II RXYQ5MY1B Service Manual

R-410a heat pump 50hz
Hide thumbs Also See for VRV II RXYQ5MY1B:
Table of Contents

Advertisement

Piping Installation Point

5. Piping Installation Point

5.1

Piping Installation Point

Connection
Kit A
Since there is a possibility that oil may be collected on a stop machine side, install piping
between outdoor units to go to level or go up to an outdoor unit, and to make a slope.
The projection part between multi connection piping kits
When the piping length between the multi connection kits or between multi connection kit and
outdoor unit is 2m or more, prepare a vertical projection part (200mm or more as shown below) only
on the gas pipe line location less than 2m from multi connection kit.
In the case of 2m or less
In the case of 2m or more
304
Connection
Kit B
Less than 2m
Less than 2m
2m or more
Vertical
Projection
200~300mm
Less than 2m
Max. 5m
Maximum length from a connection kit.
10m or less from first branch.
(Equivalent Piping Length 13m)
V3037
200~
300mm
Vertical
Projection
200~300mm
Less than 2m
SiE39-404
(V3084)
(V3085)
Appendix

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents