2.1 — Required Tools
Tools and Items Needed for Installation:
• 1/4" and 11/32" nut drivers
• Straight blade and Phillips screwdriver
• Electric drill, anchors and screws to mount transfer switch to wall
• Wire cutter/stripper
• Wire connectors
• Power Cord to connect generator to switch
2.2 — Specifications
Model
Max Generator Size in Watts
Max Amps
NEMA Configuration of Power Inlet
Voltage
NEMA Type Enclosure
Phase
Minimum Gauge / Cord Size
HAZARDOUS VOLTAGES ARE PRESENT INSIDE TRANSFER SWITCH ENCLOSURES THAT CAN CAUSE DEATH
+
OR SEVERE PERSONAL INJURY. FOLLOW PROPER INSTALLATION, OPERATION AND MAINTENANCE PROCE-
DURES TO AVOID HAZARDOUS VOLTAGES.
TURN OFF THE MAIN CIRCUIT BREAKER IN THE LOAD CENTER BEFORE STARTING INSTALLATION.
+
2.3 — Installation Procedure
Model 6375 – 15 amp Furnace Transfer Switch
1. Turn off the main circuit breaker in the load center before starting installation.
2. Furnace transfer switch can be installed to the left or right side of load center. Trial fit the unit, holding up to the
wall about 18" from the center of the load center, and mark the location of the transfer switch and end of har-
ness at load center.
3. Remove the load center cover.
Transfer Switch Installation Guidelines
Table 1: SPECIFICATIONS
6375
1875
15 Amps @ 125 Volts
5-15
125 Volts
3R - Outdoor
1
12/3
6377
7500
30 Amps @ 125/250 Volts
L14-30
125/250 Volts
3R - Outdoor
1
10/4
5