Connecting up / commissioning
5.2 Installing and commissioning the CM 1542-5
Procedure for installation and commissioning
Step
20
Execution
1
When installing and connecting up,
keep to the procedures described for
installing I/O modules in the system
manual "S7-1500 Automation Sys-
tem".
3
Connect the CM to PROFIBUS via the
RS-485 socket.
4
Turn on the power supply.
5
Close the front covers of the module
and keep them closed during opera-
tion.
6
The remaining steps in commission-
ing involve downloading the STEP 7
project data.
Notes and explanations
Lower surface of the CM
The STEP 7 project data of the CM is transferred
when you download to the station. To load the
station, connect the engineering station on which
the project data is located to the Ethernet/MPI inter-
face of the CPU.
You will find more detailed information on loading in
the following sections of the STEP 7 online help:
Downloading project data
Using online and diagnostics functions