Startup; Startup Checklist; Startup Steps For A Single Inverter - YASKAWA XGI 1000-65/65 Installation And Operation Manual

Commercial 1000vdc string inverter
Hide thumbs Also See for XGI 1000-65/65:
Table of Contents

Advertisement

Installation and Operation Guide SOLECTRIA XGI 1000 (Rev D)

4. Startup

Startup Checklist

4.1
Mechanical Installation
Make sure the mounting bracket is securely installed and all fasteners are tightened to the torque
specifications. See
Mounting the
Electrical Connections
Make sure all conductors are landed on the correct terminals.
Make sure all connections are tightened to torque specifications. See
Make sure the DC Switch on the inverter is in the "OFF" position.
Make sure the AC Switch on the inverter is in the "OFF" position.
Electrical Check
Make sure the AC circuit breaker is properly sized.
Test the AC voltage and confirm that it is within the normal operating range.
Test the polarity of DC inputs and confirm they are proper. See
Make sure the open circuit voltage of input strings is less than 1000VDC.

Startup Steps for a Single Inverter

4.2
Electrical Shock Hazard
Installer may come into contact with components that have hazardous voltage and
energy potential.
Use proper safety equipment when energizing the inverter.
Follow these instructions when turning on a single inverter.
Quick Start Guide
For more details regarding communication commissioning, see the communication Quick
Start Guide.
1. Turn ON the site AC breaker for the inverter.
2. Complete the connection of the input PV source circuits (close the fuse holders).
3. Turn ON the AC switch on the inverter.
4. Turn ON the DC switch on the inverter.
5. Verify that the Status Panel illuminates Ready and neither Maintenance nor Power Fault is illuminated.
a.
If the LEDs do not match the description above, see
b.
Verify that the Status Panel illuminates Ready, Network and Communications, and Power.
6. Connect to the gateway inverter's WiFi network, XGI-00-006 (see
DOCR-070733-D
Inverter.
AC Connections
DC
Connections.
Maintenance and
Troubleshooting.
User Interface
and
DC
Connections.
Overview).
Page 40 of 86