Preliminary Checks; Check Equipment Received; Moving And Siting The Unit - Carrier Aquaforce 30XAS Series Installation, Operation And Maintenance Instructions

Air-cooled liquid chillers. nominal cooling capacity: 232-486 kw - 50 hz
Hide thumbs Also See for Aquaforce 30XAS Series:
Table of Contents

Advertisement

2 - PRELIMINARY CHECKS

2.1 - Check equipment received

- Inspect the unit for damage or missing parts. If damage is
detected, or if shipment is incomplete, immediately file a claim 
with the shipping company.
- Confirm that the unit received is the one ordered. Compare 
the name plate data with the order.
- The unit name plate must include the following information:
• Version number
• Model number
• CE marking
• Serial number
• Year of manufacture and test date
• Fluid being transported
• Refrigerant used and refrigerant class
• Refrigerant charge per circuit
• Containment fluid to be used
• PS: Min./max. allowable pressure (high and low pressure 
side)
• TS: Min./max. allowable temperature (high and low pressure 
side)
• Relief valve set pressure
• Pressure switch cut-out pressure
• Unit leak test pressure
• Voltage, frequency, number of phases
• Maximum current drawn
• Maximum power input
• Unit net weight
- Confirm that all accessories ordered for on-site installation 
have been delivered, and are complete and undamaged.
The unit must be checked periodically during its whole
operating life to ensure that no shocks (handling accessories,
tools etc.) have damaged it. If necessary, the damaged parts
must be repaired or replaced. See also chapter 11 "Standard
maintenance".

2.2 - Moving and siting the unit

2.2.1 - Moving
See chapter 1.1 "Installation safety considerations".
In some cases vertical supports are added for the transport and
handling of the unit. These supports can be removed for access
or connection, if required. 
IMPORTANT: Follow the disassembly sequence shown in the
disassembly instruction notes.
- Unscrew screws marked 1 and 2
- Loosen screw 3, and lift and remove support 4
- Uncrew screw 5 and loosen screw 6.
- Lift and remove support 7.
- Unscrew screw 8 and remove plate 9.
9
6
7
1
3
2
2
4
1
8
5
9