SECTION 5
5.3
INITIAL START-UP
PROCEDURE
The following procedure should be used to make the
initial start-up of the compressor.
NOTE
Before initial start up check that fluid is at
proper level in the sight glass. Grease
motor per manufacturer's recommenda-
tions.
1. Read the preceding pages of this manual
thoroughly.
2. Jog motor to check for correct rotation of
main motor and fan (refer to Section 4.6).
3. Be sure that all preparations and checks
described in the Installation Section have
been made.
4. Start the compressor (manual mode
or AUTO mode
5. Open the shut-off valve to the service line.
6. Check for possible leaks in piping.
,
)
7. Slowly close the shut-off valve to assure
proper nameplate pressure unload setting is
correct. The compressor will unload at
nameplate pressure. If adjustments are nec-
essary, see Control System Adjustments.
8. Observe the operating temperature. Refer to
Section 2.3 for proper operating temperature
range. If temperature exceeds this range, the
cooling system and installation environment
should be checked.
9. Open shut-off valve to the service line.
10. Reinspect the compressor for temperature
and leaks the following day.
5.4
SUBSEQUENT START-UP
PROCEDURE
On subsequent start-ups, check that the proper level
is visible in the fluid sight glass and simply press the
START
button. When the compressor is
running,
observe
the
maintenance indicators.
5.5
SHUTDOWN PROCEDURE
To shut the compressor down, simply press the
STOP
button.
TS32 USER MANUAL
instrument
panel
and
65