These commissioning instructions describe the manual parameterization adaptations that
you have to carry out following auto commissioning.
● Follow the explanations in these commissioning instructions. This will ensure safe,
problem-free operation and maximize the service life of the motor.
These commissioning instructions apply in conjunction with the operating instructions for the
1PH8 Premium Performance motor and the commissioning manual for the SINAMICS S120
converter.
Siemens strives continually to improve the quality of information provided in its manuals and
instructions.
● If you find any mistakes or would like to offer suggestions about how this document could
be improved, contact the Siemens Service Center.
● Always follow the safety instructions and notices in these operating instructions.
The warning notice system is explained on the rear of the inside front.
Text features
In addition to the instructions that you must observe for your own personal safety as well as
to avoid material damage, you will find the following text features in these operating
instructions:
Action instructions
Action instructions to be carried out in a fixed sequence are designated using the following
symbols:
The arrow indicates the start of the action instructions.
The individual handling steps are numbered.
1. Execute the action instructions in the specified order.
The square indicates the end of the action instruction.
Action instructions without a specified sequence are identified using bullet points:
● Carry out the action instruction.
Enumerations
● Enumerations are identified by a bullet point without any additional symbols.
– Enumerations at the second level are hyphenated.