2.6
Work Flow for AIS Installations for Ships in Commission
Work Item
Acceptance of Order
Schedule confirmation
1)
Confirmation of work time
2)
Confirmation of ship inspection
3)
Preparation of documents requested by a ship owner and
confirmation of submission time
Ship inspection (confirmation using a checklist)
Preparation of work drawings (Expansion of drawings by ship
inspection)
1)
System diagram
2)
Drawing for antenna installation position (Based on the
existing antenna layout drawing and ship inspection
information)
3)
Drawing for antenna fixing pole
4)
Drawing for device installation
・
Front wall in the bridge
・
Radar indicator
・
Chart table, etc.
5)
Drawing for cable path (including fixing locations of cable
glands)
Preparation of work plan
1) Work date. (Decide a work period based on workload.)
If the work cannot be completed once (some part of the work
is saved for another day due to navigation), planning is done
to separate the installation of the equipment from the
preparatory work. (However, it is difficult to separate the work
in consideration of the supplementary work.)
2) Location of work
3) Responsible person for the work (including an agent)
4) Work application (work procedure)
①
Supplementary work
・
Removal of ceilings
・
Removal of walls
・
Working on walls for device installation, etc.
②
Hot work
・
Fixing an antenna pole
・
Mounting a cable gland
・
Fixing brackets for a device table
③
Fixing devices
④
Cabling
・
Cabling
・
Binding: Use of existing cable paths
⑤
Recovery from the supplementary work
・
Recovery of ceilings
・
Recovery of walls, etc.
⑥
Connection (Makers are responsible for external devices.)
・
Gyrocompass
・
GPS receiver
・
Speed log
・
Others
⑦
Functional test (based on the test manual)
Preparation of the work report and test report.
PREPARATION FOR INSTALLATION
Responsible
Section
Marine Sales
Department/Agent
Marine Sales
Department / TMS
Department
TMS Department /
Agent
TMS Department /
Engineering
Department
TMS Department /
Agent
TMS Department /
Agent
Note
TMS
Department
will check
the plans
prepared by
agents.
2-11