Operation Verification - Alvarion BreezeMAX PRO-S CPE Product Manual

Table of Contents

Advertisement

Chapter 3 - Commissioning
3.5

Operation Verification

To verify proper operation of the PRO-S CPE, examine the LED indicators on the
IDU (see
NOTE
Verifying the correct operation of the ODU using the SAU LEDs is meaningful only after the
configuration and alignment processes are completed, and the unit is synchronized with the Base
Station.
To verify proper operation of the Si CPE, examine the LED indicators on the top
panel (see
To verify proper connection to the end-user's data equipment, examine the
Ethernet Integrity and Ethernet Activity LEDs of the Ethernet connectors.
To verify data connectivity, from the end-user's PC or from a portable PC
connected to the unit, ping a known device in the network, or connect to the
Internet.
70
Table
2-5) and the SAU (see
Table
2-7).
Table
3-2).
BreezeMAX CPEs Product Manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Breezemax si cpe

Table of Contents