Installation: Mechanical
Figure 19. Rigging diagram with anchor hole
and bolt detail
Control
Panel
See anchor hole
detail
Anchor Bolt Detail
Nuts should not be tight.
Leave 2 to 3 mm gap.
To meet
local codes
Concrete
Recommended procedure to allow for
thermal expansion. (Unless otherwise
specified, parts are furnished by the
customer.)
56
Motor
Terminal Box
Optional unit-
mounted
starter
Unit mounting pad 13 mm
thick (by Trane)
Vibration isolator (by Trane)
75 mm steel pipe
152 ˘ 152 19 mmv
steel plate
Figure 20. Rigging diagram with safety chain placement
B
C
Anchor Hole Detail
4 ˘ 22 mm
diameter holes for
anchoring the unit
Dimensions are typical for each corner
A
B
C
Evaporator
tubesheet