SECTION 5: PRE-INSTALLATION

5.10 Pre-Installation Checklist

Be sure the following items are completed prior to
beginning installation.
Site foundation is flat and level.
Sump is complete with all necessary channels
(RFF models only).
Rotofilter will have at least 92 centimeters (36
inches) of service access on the inlet, spray bar
assembly, and drive assembly sides.
Inlet water channel has fully functioning flow
control capable of maintaining level identified
by Pentair.
Inlet water channel has monitoring system
installed (if necessary).
Appropriate connections are available and can
be made between the inlet water channel and the
Rotofilter inlet.
Outlet water channel has fully functioning flow
control capable of maintaining level identified
by Pentair.
Outlet water channel has monitoring system
installed (if necessary).
Appropriate connections are available and can be
made between the outlet water channel and the
Rotofilter outlet.
Appropriate connections are available and can
be made between the overflow channel and the
Rotofilter overflow weir (if necessary).
Backwash pump water source has
been identified.
Backwash pump electrical supply has
been identified.
Backwash electrical system has been outlined,
diagrammed, checked for accuracy, and will
not interfere with the service clearance of the
Rotofilter.
Backwash plumbing system has been outlined,
diagrammed, checked for accuracy, and will not
interfere with the service clearance of
the Rotofilter.
Control panel location has been identified,
outlined, diagrammed, and will not interfere with
the service clearance of the Rotofilter.
Existing plumbing has been thoroughly flushed.
PR Aqua Rotofilter™ Drum Filter Installation and Operation Manual
19