3.7.2 Visual Inspection of the Modules

After transporting the modules to the installation location, check for:
 Physical damage to the exterior
 Damaged or protruding screws
 Proper voltage and internal impedance of the battery modules using the battery tester.

Table 3-6: Module Voltage and Internal Impedance

No.
1
2
Internal Impedance Check
After completion, install the battery module in the previously installed rack or return the battery
module to its original packing for protection during storage.

3.7.3 Inspecting the Switchgear

After transporting the Switchgear to its installation location, check for:
 Physical damage
 Paint peeling
 Damaged or protruding screws.
After completion, install the switchgear in the previously installed rack or return the switchgear to its
original packing for protection during storage.

3.7.4 Inspecting the SMPS assembly

After transporting the SMPS Assembly to its installation location, check for:
 Physical damage
 Paint peeling
 Damaged or protruding screws.
After completion, install the SMPS in the previously installed rack or return the SMPS to its original
packing for protection during storage.
ET003222373
English 4/2018. Rev 0.0
Items
Voltage Check
.
Assembling the Product
3
Value
28.712 ~ 29.104V
3.0 ~ 4.3 mΩ
15