2.2
Commissioning Procedure Overview
COMBIMASTER 411 and MICROMASTER 411 can be commissioned
in a variety of ways as explained in sections 2.2.1 to 2.2.6 below.
Installation
Commissioning
Terminal Control
Figure 7
Commissioning Procedure Overview
10
MICROMASTER 411 & COMBIMASTER 411
Getting Started Guide – 07/05
Default
DIN1
ON/OFF1
Jumper: Pot = Run
Analogue setpoint
Default
Internal
(Control Pot.)
Reference
Source
External
Fit Potentiometer
(setpoint added to
Control Pot.)
Jumpers
Fit Jumpers
(see section
3.2.1.)
Mechanical
Installation
Electrical
Installation
BOP
Command
Source
Control
Potentiometer
BOP setpoint
Speed
Reference
Parameters (keypad)
Ramp Times
Set Ramp Parameter
Start the Motor
Parameter
P0700 = 1
Commissioning
Keypad Control
Parameter
P1000 = 1
No Jumpers
Up = P1120