Chapter 5
Installing Route Processor Cards, Fabric Cards, and Line Cards
Verifying the Installation of a Fabric Card
Figure 5-6
1 Status LED
2 Attention LED
Use the Status LED, located on the faceplate of the FC, to verify the correct installation of the card:
•
•
•
•
FC Front Panel
When the card is properly installed and no faults are detected, the card status LED turns green.
When the card status LED is solid yellow, either software initialization is in progress during bootup
or a fault exists on the board.
When the card status LED is blinking yellow, the card is not fully seated.
When the card status LED is off, verify that the card is installed correctly. There could be no power
applied to the card, a power fault, or a hardware fault.
Cisco Network Convergence System 4000 Series Hardware Installation Guide
3 Port LEDs (one per port)
Installing a Fabric Card
5-15