Figure 48. MWMA and MWMB Main Control Image
S1+S2
CCM Address
Figure 49. MWMA and MWMB Receiver Control Image (No Operation Switches on Main Control)
14. Condensate Pipe Work Installation
14.1. Outdoor Unit Condensate Piping
Condensate formed during the heating and defrost processes must be drained from heat pump units. Drain holes are
provided in the base of the units to ensure proper drainage. Heat pumps must be raised when installed on a concrete pad or
the ground to allow drainage to occur. If the heat pump unit is installed on wall mounting brackets, insert the provided drain
connector into one of the 1 inch (25 mm) drain holes and attached a field-provided insulated drain hose to the connector.
Use field-provided rubber plugs to cover any unused drain holes.