NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices and adhere to
the safety considerations/information as outlined in preceding sec-
tions of this Installation Instructions document.
Machine Model Number: 19XRV Serial Number:
To:
Attn:
The following information provides the status of the chiller installation.
1. The machine is level.
2. The machine components are installed and connected in
accordance with the installation instructions.
3. The isolation package and grouting (if necessary)
are installed.
4. The relief valves are piped to the atmosphere.
5. All piping is installed and supported. Direction of flow
is indicated in accordance with the installation instructions
and job prints.
a. Chilled water piping
b. Condenser water piping
c. Waterbox drain piping
d. Pumpout unit condenser piping (if installed)
e. Other
6. Gages are installed as called for on the job prints required
to establish design flow for the cooler and condenser.
a. Water pressure gages IN and OUT
b. Water temperature gages IN and OUT
7. The machine's VFD wiring is complete. The wiring is
installed per installation instructions and certified prints.
a. Power wiring to VFD circuit breaker. (If chiller was
disassembled during installation, motor leads must
not be taped until the Carrier technician megger tests
the motor.)
b. Oil pump wiring
c. Oil heater/control wiring
d. Carrier controls can independently energize water pumps
and tower fan
e. Line side voltage is within ±10% of chiller nameplate voltage
f. Other
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53190042-01
INSTALLATION START-UP REQUEST CHECKLIST
Printed in U.S.A.
Date
Project Name
Carrier Job Number
YES/NO
(N/A)
Form 19XRV-CLT-5SI
Pg CL-1
DATE TO BE
COMPLETED
12-16
Replaces: 19XRV-CLT-4SI

Advertisement

Table of Contents
loading

Table of Contents