The aggregates (pumps, actuators, etc.) connected to the outputs can be switched.
In the case of modulating outputs, a signal can be delivered in the relevant value range.
The application is deactivated during the wiring test. The outputs are in a defined OFF
state; safety-related functions are deactivated.
In the wiring test, the inputs and outputs are to be checked for the following faults:
• Wiring error, that is, wires have been mixed up
• Position fault, that is, wires of sensor or actuator have been mixed up
• Discrepancy between actual type of connection and controller configuration (e.g. LG-
Ni 1000 in place of DC 0...10 V)
Main menu > Commissioning > Wiring test > Boiler 1 > Inputs
Operating line
Actual value boiler temperature
Main menu > Commissioning > Wiring test > Boiler 1 > Outputs
Operating line
Boiler pump
3.7

Concluding commissioning

If the application is correct, the "Commissioning" menu can be quit as follows:
Press the ESC button. The display shows a dialog box with the following informa-
1.
tion:
Caution!
Plant starts
ESC
2.
Confirm by pressing the OK knob. Then, the controller starts using the settings
made; the plant is started up, and the main menu appears on the display.
Main menu
Commissioning...
Boiler sequence manager...
Boiler 1...
Boiler 2 ...
3.8

Data backup

When commissioning is completed, the entire commissioning data set (configuration
and all settings) can be stored in the controller. If any time later, an unauthorized per-
son readjusts important values, this function can be used to restore the proper con-
trolled state after commissioning.
Main menu > Data backup
Operating line
Storage date
Storage year
Boiler Sequence Controller RMK770
3 Commissioning
Remarks
Display of the current measured value
Positions
Off / On
OK
Remarks
Display of the date on which the commis-
sioning data set was downloaded to the
controller's memory
Display of the year in which the commission-
ing date set was downloaded to the control-
ler's memory