Water-cooled variable speed screw chiller

Advertisement

Quick Links

Supersedes Form 201.30-CL2 (412)
CUSTOMER: _________________________________
ADDRESS: __________________________________
PHONE: _____________________________________
JCI TEL NO: ____________________ JCI ORDER NO: ________________ JCI CONTRACT NO: ____________
chilleR MODel NO: ____________________________
The work (as checked below) is in process and will be completed by:
The following work must be completed in accordance with start-up instructions contained in the installa-
tion, Operation, and Maintenance Manual (Form 201.30-icOM2):
A. GeNeRAl:
The following basic checks should be made with the
customer power to the unit switched off.
1. Review the Installation Checklist (Form 201.30-
CL1). ..................................................................
2. Inspect the unit for installation damage that may
have occurred. If damage is found, take action
and/or repair as appropriate. ...............................
3. Water connection inlet and outlet are at proper
locations, have hangers nearby that would sup-
port their weight and show no visible strain on
chiller nozzles. ...................................................
4. Wiring is complete (power feed terminations in
the VSD), and all sources of electrical supply to
the unit are taken from a single point of isolation
per 201.30-PW2. ................................................
5. Confirm any field control wiring modifications
are in accordance with Form 201.30-PW2 .........
6. Verify the chiller is charged with refrigerant
(pressures match R-134a saturation for ambient
temp). .................................................................
7. Verify that the unit's protective ground terminal(s)
are properly connected to a suitable grounding
point. Ensure that all unit internal ground con-
nections are tight. ...............................................
8. Verify the following isolation valves are open.
a. Compressor 1 discharge (optional) ...............
b. System 1 condenser subcooler outlet (option-
al) ...................................................................
c. System 1 main oil supply inline ball valve ......
d. System 1 condenser pressure transducer .....
e. System 1 condenser gas to oil eductor .........
JOHNSON CONTROLS
START-UP checkliST
JOB NAME: _________________________________
LOCATION: _________________________________
CUSTOMER ORDER NO: ______________________
UNiT SeRiAl NO: ___________________________
_____________ / ____________ /
f. System 1 evaporator pressure transducer ....
g. System 1 evaporator oil return to eductor .....
h. System 1 oil return eductor to compressor ....
i. System 1 liquid injection to compressor (op-
tional) .............................................................
j. System 1 economizer pressure transducer ...
k. Compressor 2 discharge (optional) ...............
l. System
(optional) ........................................................
m. System 2 main oil supply inline ball valve ......
n. System 2 condenser pressure transducer .....
o. System 2 condenser gas to oil eductor .........
p. System 2 evaporator pressure transducer ....
q. System 2 evaporator oil return to eductor .....
r. System 2 oil return eductor to compressor ....
s. System 2 liquid injection to compressor (op-
tional) .............................................................
t. System 2 economizer pressure transducer ...
9. Verify the shipping anti-freeze solution has been
drained from the VSD, and replaced with the
proper amount of inhibited water coolant that
shipped loose with the chiller. Refer to SEC-
TION 7 - MAINTENANCE in the 201.30-ICOM2
for filling process. ...............................................
10. Verify electrical connections in the VSD are
tight, especially motor leads to terminals. ..........
11. If the VSD provides an optional circuit break-
er at the incoming power connection to
the VSD, make sure the settings are prop-
erly set per the information on the next page.
Form 201.30-CL2 (912)
MODel – YVWA
___________
Month
Day
1
condenser
subcooler
(continued on following page)
Year
outlet
1

Advertisement

loading

Summary of Contents for York YVWA

  • Page 1 Supersedes Form 201.30-CL2 (412) Form 201.30-CL2 (912) MODel – YVWA START-UP checkliST CUSTOMER: _________________________________ JOB NAME: _________________________________ ADDRESS: __________________________________ LOCATION: _________________________________ PHONE: _____________________________________ CUSTOMER ORDER NO: ______________________ JCI TEL NO: ____________________ JCI ORDER NO: ________________ JCI CONTRACT NO: ____________ chilleR MODel NO: ____________________________...
  • Page 2 FORM 201.30-CL2 ISSUE DATE: 9/30/2012 13. Check the chiller for refrigerant leaks at joints or 12. Find your VSD model from the list below, water piping leaks..........and set the adjustments to the setting val- ues in the following table. If your model is 14.
  • Page 3 FORM 201.30-CL2 ISSUE DATE: 9/30/2012 7. Record the overload settings below: liquid control Setpoint System 1: __________________________Amps Program the chilled and condenser liquid (optional heat pump) setpoints and ranges, then record them below: System 2: _________________________ Amps 1. Leaving Chilled Liquid Temp Setpoint = ______________________°F (°C) Setting the potentiometers incorrectly...
  • Page 4 12. After the chiller is at full load at Design Leaving Chilled Liquid Temperature, capture the operat- ing data to print or save to text file..... P.O. Box 1592, York, Pennsylvania USA 17405-1592 800-861-1001 Subject to change without notice. Printed in USA Copyright ©...