Installation Of The Decoration Panel; Test Operation - Daikin FBQ60BV1 Installation Manual

Ceiling mounted cassette built-in type
Hide thumbs Also See for FBQ60BV1:
Table of Contents

Advertisement

5. Control by 2 remote controllers
(Controlling 1 indoor unit by 2 remote controllers)
• When using 2 remote controllers, one must be set to "MAIN" and the other to "SUB".
MAIN/SUB CHANGEOVER
(1)Insert a
screwdriver into the recess between the upper and lower part of remote controller and,
working from the 2 positions, pry off the upper part. (The remote controller PC board is attached to
the upper part of remote controller.) (Refer to Fig. 25)
(2)Turn the MAIN/SUB changeover switch on one of the two remote controller PC board to "S".
(Leave the switch of the other remote controller set to "M".) (Refer to Fig. 26)
Upper part of remote controller
Insert the screwdriver here and gently
work off the upper part of remote controller.
Fig. 25
Wiring Method (See ''8. ELECTRIC WIRING WORK'' on page 12)
(3)Remove the control box lids.
(4)Add remote control 2 (slave) to the terminal block for remote controller (P
box. (There is no polarity.) (Refer to Fig. 23 on page 15 and Table 2 on page 12)

11. INSTALLATION OF THE DECORATION PANEL

Refer to the installation manual attached to the decoration panel.
After installing the decoration panel, ensure that there is no space between the unit body and decoration
panel.

12. TEST OPERATION

Refer to the section of "FOR THE FOLLOWING ITEMS, TAKE SPECIAL CARE DURING CON-
STRUCTION AND CHECK AFTER INSTALLATION IS FINISHED" .
• After finishing the construction of refrigerant piping, drain piping, and electric wiring, conduct test operation
accordingly to protect the unit.
1. How to test operation
1. Open the gas side stop valve.
2. Open the liquid side stop valve.
3. Electrify crank case heater for 6 hours (Not required in case of a unit exclusively designed for cooling
only).
4. Set to cooling operation with the remote controller and start operation by pushing ON/OFF button (
5. Press INSPECTION/TEST OPERATION button (
ler) and operate at Test Operation mode for 3 minutes.
6. Press INSPECTION/TEST OPERATION button (
7. Confirm function of unit according to the operation manual.
17
(Factory setting)
Lower part of
remote
controller
(Only one remote controller
needs to be changed
if factory settings have
remained untouched.)
S
S
M
S
M
Fig. 26
) 4 times (2 times for wireless remote control-
TEST
) and operate normally.
TEST
Remote controller
PC board
, P
) in the control
1
2
).
English

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fbq71bv1Fbq60bvlFbq71bvl

Table of Contents