Install XY table
1- un-pack the XY table components from the cartoon
2- Insert the main two rail bars to the X and Y holder sliding block.
3- Connect the bars with the left and right fixtures.
4- Install the four legs to the fixture.
5- Insert the limit control rod as a final step.

System installation

 Please make sure that the supply voltage accords with the rated voltage
on the system nameplate then connect the power cord.
 Check whether all switches are turned off.
 Connect the two thermocouples in the first and second thermocouple
female sockets ( 1 & 2 from right to left)
 Insert the vacuum tube into suction pump nozzle