Installing indoor unit
(1) For the piping distribution of indoor unit, please refer to Fig. 11-5 and 11-6. When piping on the
left or right side, it is required to cut the tailing portion for piping left on the baseboard of the
main unit, as shown in Fig. 11-7.
When only power cord is led out, it should go through the hole;
Cut off tailings 1 when both the connection cord and wire are led out.
(2) Wrap the connecting piping and electric cable properly (as shown in Fig. 11-8) and pass them
through the piping hole.
(3) Hang the claw behind the indoor unit on the pothook on the wall rear panel, move the unit left
and right to check if the body is firm.
(4) Guarantee that the install height of the indoor unit should above 2.3m from the floor
①Right piping
Fig. 11-7
②Right rear piping
Fig. 11-5
Taping 2
Signal control line
Taping 1
(for heat pump only)
through-hole
—88—
④Left rear piping
③Left rear piping
Fig. 11-6
Power connection cord
Drainage pipe
Connection pipe
Wrapping tape
Fig. 11-8