Connect all plugs as labelled in the control box.
Screw the earth cable from the machine and the main switch to earth point A.
Connect earth point A and earth point B with an earth cable.
Screw the earth cable of plug 1 to earth point B.
Clean the machine thoroughly.
Check the oil level, see Chapter 12 Care and Maintenance.
Check the machine, especially the electric wires, for any damage.
Have specialists check, whether the machine's motor can be used with the existing
mains voltage.
Circuit diagrams, see Chapter 13.
Switching the machine on/off, see Chapter 7.01 Main switch.