INSTALLATION REQUIREMENTS

The installation must conform to the requirements of the authority
having jurisdiction or, in the absence of such requirements, to the
National Fuel Gas Code, ANSI Z223.1-latest edition.
This installation must also conform to the additional requirements
in this Slant/Fin Instruction Book.
Burners
NATURAL GAS-FIRED BOILER LOCATION
Pilot
Provide a level, solid foundation for the boiler. Location should be
as near as possible to chimney or outside wall so that the flue
pipe from boiler is short and direct.
Burner
Access
The location should also be such that the gas ignition system
components are protected from water (dripping, spraying, rain,
Door
etc.) during appliance operation and service (circulator replace-
ment, condensate trap, control replacement, etc.).

BOILER FOUNDATION

A. Provide a solid, level foundation, capable of supporting the
weight of the boiler filled with water, and extending at least 2"
past the jacket on all sides. See dimensions of boiler, page 2.
Gas Valve
B. For installation on non-combustible floors only. The
Combustible Floor Kit part number printed on the boiler rating
plate is the only one to be used when installing on com-
bustible floors. The boiler must not be installed on carpeting.
C. If boiler is to be located over buried conduit containing electric
wires or telephone cables, consult local codes or the National
Board of Fire Underwriters for specific requirements.
3

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Se-245Sentinel se-245Sentinel se-70Sentinel se-105Sentinel se-210Sentinel se-140 ... Show all

Table of Contents