Pump & Controller (See page 30 - 39 for more detail)
Pump and controller is securely mounted on a wall to the side of the tank (within
500mm of the tank.) The power supply lead to the pump and controller is 1500mm in
length.
A continuous supply power point is within 1.5 metres of the controller.
Run sensor leads to the tank and panels (it is recommend that the sensor leads are
protected from the elements and mechanical damage)
Gas Booster (See page 23 - 29 for more detail)
Booster is mounted on either the left or right hand side of the tank
The 75c bridge is fitted to the booster. (See page 29 for more detail)
A continuous supply power point is within 1 metre of the booster.
Booster is fitted in accordance with the manufacturer‟s installation instructions,
AS3500.4. AS3000 wiring regulations (in New Zealand NZBC G12), AS 5601 & NZS
5261 and all Local Building, Water regulations.
Commissioning the system
Once the installation is complete the system will need to be filled with water and
commissioned.
First flush all piping of debris.
Turn the water isolation valve on at the tank.
Check pipework for leaks.
Open household taps individually and purge out any air.
Open vent on auto vent cap (At panels).
For electric boost turn power supply onto tank.
Turn power supply onto Controller/Pump station
For gas boost turn on isolation valves at booster.
Plug in three pin plug to power supply and turn on
Commission booster (See page 29 for more detail)
Check and adjust temperature control valve
6