2.0 TECHNICAL DATA

2.1 Overall dimensions are shown in Figure 2.1 (p3).
Both single and multiple boiler arrangements are
shown.
The Warmwell boiler can be installed as a single
unit or in modular form where a 'multi' casing
reduces required floor area.
independent door for access to the controls and
other working components.
It is recommended that a maximum of 6 boilers can
be positioned on 533mm (21") centres if required.
Larger numbers should be split into two or more
banks with 150mm (6") between each bank. NOTE!
To install modular units on 533mm (21") centres, the
casing support rail or spacing plates should be fitted
between each boiler before bolting together. See
Section 10.1: General Installation of Boilers (p16)
Ref.: - spacing plates for further information. See
Figure 2.1 (p3) re: - coupling of Warmwell and
Purewell boilers. The boiler can also be installed in
a 'stand alone configuration' if required.
2.2 General Information and Technical Data relating
to Natural Gas is shown in Figure 2.2 (p4).
Technical data relating to propane firing can be
found in Appendix 'A' (p41).
2.3 Screw threads: All screw threads used in the
Warmwell boiler conform to the following: -
ISO 7/1 or ISO 228/1 for pipe threads where
applicable. ISO 262 for all general screw threads.

3.0 GENERAL REQUIREMENTS

3.1 Related Documents

Gas Safety Installations and Use Regulations
1998, (As amended).
persons in accordance with the above regulations
install all gas appliances.
appliances correctly could lead to prosecution. It is
in your own interest, and that of safety, to ensure
that this law is complied with.
The installation of the boiler MUST be in accordance
with the relevant requirements of the Gas Safety
Regulations, Building Regulations, IEE Regulations
and the bylaws of the local water undertaking.
The installation should also be in accordance with
any relevant requirements of the local gas region
and
local
authority
recommendations of the following documents: -
British Standards
BS 7074: Application, selection and installation of
expansion vessels and ancillary equipment for
HAMWORTHY HEATING LTD
Each boiler has an
It is law that competent
Failure to install
and
the
relevant
sealed water systems. Part 2: Code of practice for
low and medium temperature hot water systems.
BS 6891: Installation of low pressure gas pipework
of up to 28mm in domestic premises (for larger
installations see IGE/UP/1, IGE/UP/1A and IGE/
UP/2)
BS 6644: Installation of Gas Fired Hot Water
Boilers - 60kW to 2MW.
BS
6700:
maintenance of services supplying water for
domestic use.
BS 6880: Part 1, 2 & 3: Code of practice for low
temperature hot water heating systems of output
greater than 45kW.
BS EN 60335, Part 1. Safety of Household & similar
electrical appliances. BS 3456, Part 201: Electrical
Standards.
CP 342: Centralised hot water supply.
Buildings other than individual dwellings.
I. Gas E. Publications
IGE/UP/1
industrial and commercial gas installations.
IGE/UP/1A Soundness testing and direct purging of
small low pressure industrial and commercial natural
gas installations.
IGE/UP/2 Gas installation pipework, boosters and
compressors in industrial and commercial premises.
IGE/UP/10 Installation of gas appliances in industrial
and commercial premises Pt 1 flued appliances.
Health and Safety Executive: -
Guidance note PM5 - Automatically controlled
steam and hot water boilers.
CIBSE Publications: - "CIBSE Guide"
It is impractical in this document to specify all
relevant information, but the following extracts from
the above references are emphasised since failure
to comply with these requirements will almost
certainly result in an unsatisfactory installation.

3.2 Feed Water Quality

If the boiler feed water has a high degree of
hardness, it is recommended that the water be
treated to prevent precipitation of scale or sludge in
the boiler water passageways. Details of additives
can be obtained from any reliable manufacturer of
water treatment products or the local water
authority.
5
WARMWELL
Design,
installation,
Soundness testing and purging of
testing
and
Part 2:
500001091/F

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Warmwell 80Warmwell 120Warmwell 95Warmwell 140

Table of Contents